New Residents Permit Zones

Resident permit parking schemes may be offered to assist residents living in areas where on-street parking demand significantly exceeds supply and where it is not appropriate to manage parking problems using conventional parking restrictions. The criteria for implementing these are covered in the RPZ Policy and RPZ Operational Guidance.

In order for a Resident Permit Zone (RPZ) to be considered initially, the following criteria must all be met:

  • There should be early evidence of resident and District Councillor support for an Resident Permit Zone (RPZ) (e.g. petition, build-up of email requests or letters) 
  • At least 50% of properties in the proposed area as a whole should have no off-street parking (survey required)
  • The kerb space occupied by non-residents’ vehicles should be greater than 10% at times when parking problems caused by non-residents occur (survey required)
  • There should be sufficient kerb space to enable a minimum of 50% of all households within the proposed scheme area to park at least one vehicle on-street (survey required).

In addition there should be section 106 funding identified to cover set up costs.

The process and timeline for implementing an Resident Permit Zone (RPZ) is broadly as follows:

ActionTimeframe 
Initial survey to assess parking behaviours, capacity and occupancy2-3 months
Scheme design, assessing location and possible restrictions2 months
Consultation with statutory bodies and informal consultation with residents to obtain feedback2 months
Scheme re-design where needed1-2 months
Formal consultation on proposals2-3 months
Analysis of results and formal decision to proceed2-3 months
Issuing of statutory public notices and setting of start date1-2 months
Implementation/ start1-2 months

From start to finish bringing in a new scheme can take around 18 months. Please contact your District Councillor if you feel an Resident Permit Zone (RPZ) should be considered in your area.

 

 

Feedback