The two developers have launched a new website: gilston.info which will record information such as planned construction works and provide a means for the community to report any estates management issues.

Construction related works are underway on the Central Stort Crossing scheme (reference 3/19/1046/FUL) with works on the Eastern Stort Crossing (reference 3/19/1051/FUL) to follow later in 2026.

Improvement works were recently complete on the Fiddlers’ Brook Footbridge (reference 3/19/1049/LBC)

Essex County Council are delivering the first part of the Sustainable Transport Corridor from the Burnt Mill Roundabout to Harlow Town Centre, with works due to be completed by end of 2025