Grange Paddocks Development - Key Milestones

A list of key activities and dates for the development of Grange Paddocks.
Key Milestones - Grange Paddocks Development
Milestone Date
Wilmott Dixon start on site 23 March 2020
Hoarding complete April 2020
Existing pedestrian bridge removed April 2020
Temporary bridge installed April 2020
Haul Road installed May 2020
Water main diversion complete May 2020
Excavation of site May 2020
Fill foundations and install ground beams May - July 2020
Learner pool concrete works June - July 2020
Plant room concrete works and roof slabs June - July 2020
Competition pool concrete works June - August 2020
Steel frame erected July - August 2020
Electrical upgrade complete  August 2020
Foul drainage August - October 2020
Fire protection to structural frame August - October 2020
Decorate steel in pool hall August - September 2020
Roof works August 2020 - January 2021
Block work (substructure) September - October 2020
Learner pool filtration and pool surrounds ready for testing September - October 2020
Upper floor slabs September - October 2020
First floor plant room works September 2020 - April 2021
Competition pool filtration and pool surrounds ready for testing October - November 2020
Foul drainage - internal drainage October - November 2020
Confidence pool works ready for testing October - December 2020
Ground floor slabs October - December 2020
Facade (including installation of timber cladding) October 2020 - April 2021
Storm water drainage October 2020 - August 2021
First floor block work November 2020 - February 2021
Cafe, viewing area and circulation space November 2020 - August 2021
Football change block walls December 2020 - February 2021
Changing room village blockwork December 2020 - February 2021
Learner pool finishes December 2020 - February 2021
Offices, kitchen, servery works December 2020 - July 2021
Main office finishes December 2020 - July 2021
Landscaping and paving December 2020 - August 2021
Plant room block work January 2021 - March 2021
Roof plant works January 2021 - May 2021
Stairwells erected and finalised January 2021 - June 2021
Ground floor WCs January 2021 - June 2021
Confidence pool finishes January 2021 - July 2021
Ground floor studio and multipurpose room January 2021 - August 2021
Pool Hall   January 2021 - August 2021
First floor fitness suite January 2021 - August 2021
Spectator seating installed February 2021 - July 2021
First floor studio February 2021 - July 2021
Wet change area February 2021 - August 2021
Football pitch changing February 2021 - August 2021
External doors and louvres installed   March 2021
Learner pool tiling March 2021 - May 2021
Ground floor plant room works March 2021 - August 2021
Main pool tiling April 2021 - June 2021
Confidence water tiling May 2021 - June 2021
Leaner pool moveable floor installed May 2021 - June 2021
Outdoor play area May - July 2021
External works May 2020 - August 2021
Confidence play equipment installed July 2021
Completion date October 2021