F16/653

Planning Performance Agreements

Request Description

I am writing to you under the Freedom of Information Act 2000 to kindly request the following information from the authority's planning department

The total number of times an extension to a Planning Performance Agreement PPA has been requested to house builders in the past five years

The reasons why an extension has been requested

The number of properties that have been refused planning permission in the past 5 years in the authorities' area

The total number of applications to the authority in the past 5 years

The number of times an application has gone beyond 12 weeks in 5 years

The number of times an application has taken more than 6, 12, 18 and 24 months in the past five years

Request Date20 September 2016
Requested byMedia
Released Date  

19 October 2016

Response
  • Extensions to PPAs - NIL
  • Reasons - NA
  • No properties refsued PP: 1823
  • applications in last 5 years: 11874
  • No of times application beyong 12 weeks in 5 years: 543
  • No of times application has taken more than period below in last 5 years
    • 6 months: 203
    • 12 months: 68
    • 18 months: 44
    • 24 months: 16
 Refused

 

Refusal