Project phasing

Information on the phases and timescale of the project.

In order to keep the leisure centre operational throughout the works, the project is being delivered in phases.

During the first phase the pool hall and associated changing rooms were refurbished to improve the swimming pool facilities for customers.

This work is now complete and the swimming pool re-opened to the general public on 20 May 2022 (swimming lessons on 23 May).

Pool timetable details are on the Everyone Active website.

Refurbishment of the downstairs dry changing areas.  These were opened when the swimming pool re-opened for public use on 20 May 2022.

During the third phase, the front of the building will be demolished and a new two storey extension and external works will be constructed.  This includes the creation of the new gym, new studios, soft play facilities, cafe area and external landscaping. 

In order to carry out this phase, a temporary studio has been located in the rear car park of the leisure centre.  The gym and pool facilities will remain open during this phase of the works.

 

 

During the final phase, the upstairs of the existing leisure centre will be converted into a changing facility and spin studio. 

The new extension and pool facilities will be open during this phase.

During phases one to three of the construction, customer access will be temporarily located at the rear of the leisure centre. Footpaths and signage have been installed to make clear where the entrance is located.  

Further information can be found on Everyone Active’s website